MMRDA awards ₹129.63 crore contract for Multimodal Integration on Mumbai Metro Lines 4 & 4A
First U-Girder installed on JLN Stadium–Infopark Corridor of Kochi Metro Phase 2
Kolkata Metro Marks 41 Years of Service to the City of Joy
DMRC to introduce Driverless Trains on Delhi Metro Phase 4 Corridors
Karnataka proposes Centre of Excellence for Railways and Mobility Innovation
Egypt and Japan approve Greater Cairo Metro Line 4 Project
Metro Rail Today continues its legacy as Official Media Partner for 18th Urban Mobility India 2025
Alstom bags €1.4 billion contract from SNCF Voyageurs to supply 30 Very High Speed Trains
Nokia and ST Engineering partner to deploy communications network on Bangkok Metro’s Orange Line
How Mumbai Built Its Deepest Aqua Line Metro Project — And Won the City’s Heart?
Kanpur, India (Metro Rail Today): The Uttar Pradesh Metro Rail Corporation Limited (UPMRC) has reached another significant milestone in the ongoing construction of the Baradevi-Naubasta elevated section, part of Corridor-1 (IIT to Naubasta) of the Kanpur Metro Rail Project. Completing the casting of all pre-cast structures—U-girders, I-girders, double T-girders, and pier caps—along this approximately 5 km section marks a crucial accomplishment. These structures undergo pre-casting at the Naubasta casting yard before being skillfully erected at designated locations within the corridor, facilitated by cranes.
The final U-girder, numbered 348th, was recently cast at the Naubasta Casting Yard of the Kanpur Metro. Preceding this achievement, all pier caps and double T-girders had been cast by March 2024, followed by the completion of all I-girders by April 2024. This concludes the casting process for all 348 U-girders, 64 I-girders, 264 double T-girders, and 186 pier caps essential for the Baradevi-Naubasta elevated section, achieving a full 100 per cent completion.
Expressing happiness on this significant milestone, Shri Sushil Kumar, Managing Director of UPMRC, remarked, "The civil construction endeavours for the Baradevi-Naubasta elevated section of the Kanpur Metro project are advancing swiftly. Completion of casting of all pre-cast structures—pier caps, U-girders, I-girders and double T-girders, among others—at the Naubasta casting yard signifies our commitment to expeditious yet quality-driven construction practices. Embracing pre-cast structures in our elevated infrastructure enables accelerated progress while ensuring uncompromised quality. Following the successful launch of commercial service on the priority section (IIT to Motijheel) within the stipulated timeline in December 2021, we are diligently advancing on the remaining sections of Corridor-1."
Currently, alongside the Baradevi-Naubasta elevated section, part of Corridor-1 (IIT to Naubasta) of the Kanpur Metro Rail Project, construction is swiftly advancing on two underground sections: Kanpur Central-Transport Nagar and Chuniganj-Nayaganj. Additionally, construction has also commenced on the Rawatpur-Double Pulia underground section of Corridor-2 (CSA to Barra-8).