Nagpur broad-gauge Metro is a commuter rail project planned for the city of Nagpur and extending up to adjacent areas of Wardha, Yavatmal, Narkhed,Ramtek,Bhandara,Amravati,Wadsa and Chhindwara (also Nagbhid in the near future) in Vidarbha region of Maharashtra, India. This project will be executed by Maharashtra Metro Rail Corporation Limited.
Project Summary
- Project Name: Nagpur Broad Gauge Metro Rail Project
- Owner: Maharastra Metro Rail Corporation, Govt. of Maharashtra and Central Railway (CR)
- Operator: Maharashtra Metro Rail Corporation (Maha Metro)
- Project Type: Mass Rapid Transit System (MRTS)
- Total Network: 268.63
- Project Cost: INR 333.60 Crore
- Funding Pattern: Govt of Maharashtra, Govt. of India and KfW
- Completion Target: 2022
Operational Routes
NA
Fares
Not yet decided as project in now under construction.
Route Map
NA
Project Information
Corridor I: Nagpur - Wardha
- Route Length: 78.8 km
- No. of Stations: 13
- Station Names: Nagpur Junction, Ajni, Khapri, Gumgaon, Bori, Borkhedi, Sindi, Tuljapur, Dahegaon, Seloo Road, Varud, Sewagram and Wardha Junction
Corridor II: Nagpur-Narkhed
- Route Length: 85.53 km
- No. of Stations: 11
- Station Names: Nagpur Junction, Godhani, Bharatwada, Kalmeshwar, Kohali, Sonkhamb, Metpanjra, Katol, Kalambha, Tinkheda and Narkhed Junction
Corridor III: Nagpur-Ramtek
- Route Length: 41.6 km
- No. of Stations: 7
- Station Names: Nagpur Junction, Kalamna, Kamptee, Kanhan Junction, Dumri Khurd, Amdi Halt and Ramtek
Corridor IV: Nagpur-Bhandara Road
- Route Length: 62.7 km
- No. of Stations: 8
- Station Names: Nagpur Junction, Kalamna, Kamptee, Kanhan Junction, Chacher, Rewral, Khat and Bhandara Road
- Depot: Khapri
Project Cost & Funding:
Phase |
|
Project Cost |
|
Funding By |
|
|
₹ 333.60 Crore |
|
Govt. of India, Govt. of Maharashtra and KFW |
Deadline: NA
Technical Information
- Design Speed: 200 kmph
- Average speed: 160 kmph
- Track Gauge: Broad Gauge
- Electrification: NA
- Signalling System: Communications-based Train Control (CBTC)
- Rolling stock: NA
Major Contracts
- UMTC Limited: General Consultancy
Progress So Far
- July 2018: An MoU signed between the Government of Maharashtra, Central Railway and Maharashtra Metro Rail Corporation (Maha-Metro).
- November 2019: Railway Board approved the detailed project report (DPR) of the project.
- October 2020: Maharashtra Government cabinet approved the DPR of the project.