Surat, India (Metro Rail Today): The Gujarat Metro Rail Corporation Ltd (GMRC) has recently opened technical bids for supply of 750 V DC Third Rail electrification system for Surat Metro Rail Project Phase 1. A total of seven firms have submitted their bids for the contract package EP-1/2022.
Tender notice for Supply, Erection, Testing and Commissioning of Power Supply receiving & Distribution System, 750 V DC Third Rail Traction electrification and SCADA System for Phase 1 of Surat Metro Rail Project was issued in February 2022.
GMRC has received a total of seven bids from the following firms:-
750VDC Third rail system is more suitable for installation in tunnels with smaller clearance than overhead conductive wire systems. Third rail system also reduces the maintenance workload.
The Phase 1 of Surat Metro Rail Project is comprises of two lines with combined length of 40.35 km and 37 stations.