Contractor prequalification deadline for Dubai Metro Gold Line is extended to October 9
Indore Metro Rail Network expands to 17 km as Priority Corridor 2 opened to public
Jaffer PC appointed as Managing Director of Bangalore Metro Rail Corporation (BMRC)
CMRL appoints Systra to prepare Multi-Modal Integration DPR for Chennai Metro Phase 1 stations
BEML secures additional ₹180.60 crore Rolling Stock Order for Vande Bharat Sleeper Trainsets
Titagarh Rail Systems and Siemens join hands to explore Global Metro Rolling Stock opportunities
Rajasthan reviews DPR and funding plan for Delhi-Gurugram-Alwar Namo Bharat RRTS Corridor
Govt of India approves DPR of 671-km Hyderabad-Mumbai High Speed Bullet Train Project
GHV India bags ₹123.96 crore Civil Contract for Mall Road Depot of Agra Metro Rail Project
Govt of India approves ₹18,130.55 crore Mumbai Metro Line 5 and 5A
Bengaluru, India (Metro Rail Today): The Bangalore Metro Rail Corporation Limited (BMRCL) has awarded two track contracts (Package T1 & T2) with combined value of Rs 500.94 crore to Larsen & Toubro Ltd (L&T) for installation of track for 56 kilometres Blue Line (Corridor 5) of Bangalore Metro Rail Project, Phase 2A & 2B on 2nd June 2023.
Scope of Work: Design, supply, installation, testing and commissioning of ballast less track of standard gauge (approximately 57 Track KM) in elevated viaduct section between Silk Board Metro station (Km. 0.00) to Krishnarajapuram Metro station (Km. 18.236) & between Krishnarajapuram Metro station (Km. 0.00) to Kempapura Metro station (Km. 10.200) and in Baiyappanahalli Depot, along with ballasted track in Baiyappanahalli depot of Bangalore Metro Rail Project, Phase-2A & 2B.
Contract Value: Rs 268,46,85,571/-
Scope of Work: Design, supply, installation, testing and commissioning of ballast less track of standard gauge (approximately 51 Track KM in elevated viaduct section and 2 Track KM in Cut & Cover section) between Kempapura Metro station (Km. 10.200) to Airport Metro Station (Km. 36.530) and in Airport Depot along with ballasted track in Airport depot of Bangalore Metro Rail Project, Phase-2B.
Contract Value: Rs. 232,48,02,577/-
Package T1’s scope includes the entire ORR Line and a part of Airport Line between KR Puram – Kempapura, while Package T2’s scope includes the Airport Line’s Kempapura – Airport section.
Tender notices for the both contract packages were invited in October 2022 with 3 years work completion deadline.
L&T will install ballast less track of standard gauge on approx. 110 km elevated viaduct under Phase 2A & 2B. The ORR Line (Phase 2A) and Airport Line (Phase 2B) of Bangalore Metro Rail Project will connect Silkboard – KR Puram – Bengaluru International Airport through 30 stations on the Outer Ring Road and NH-44.
For more details, please explore the Bangalore Metro page of Metro Rail Today.