Bi-RIDE Invites Bids for Two Civil Packages for Bengaluru Suburban Rail Project Corridor 4

MRT Online Desk Posted on: 2026-11-28 16:38:00 Viewer: 84 Comments: 0 Country: India City: Bengaluru

Bi-RIDE Invites Bids for Two Civil Packages for Bengaluru Suburban Rail Project Corridor 4

Bengaluru, India (Rail & Metro Today): Bengaluru Suburban Rail Infrastructure Development (Bi-RIDE) has invited tenders for two civil construction packages under Corridor 4 of the Bengaluru Suburban Rail Project (BSTP). The packages cover elevated viaducts, at-grade formation works and associated infrastructure at different locations along the corridor.

The tenders include Corridor 4 Package 3, covering works between Bellandur and Benniganahalli, and Corridor 4 Package 4, covering the Jakkur–Rajanukunte section. Both packages exclude station works.

The last date for submission of bids for both packages is January 6, 2027.

Corridor 4 Package 3: Bellandur to Benniganahalli

Package 3 involves the design and construction of approximately 3.086 km of at-grade formation works and 4.357 km of elevated viaduct.

The at-grade works include embankments, cuttings, blanketing, minor and major infrastructure structures, retaining walls, drains, boundary walls and fencing. The package also includes an elevated viaduct with a reinforced cement concrete (RCC) ramp and associated infrastructure.

The work location is the Bellandur–Benniganahalli section, excluding stations.

Bids for Package 3 must be submitted by 3:00 PM IST on January 6, 2027.

Corridor 4 Package 4: Jakkur to Rajanukunte

Package 4 covers the design and construction of 5.277 km of elevated viaduct with an RCC ramp, including a 1.743-km double-decker viaduct.

The double-decker structure will accommodate Corridor 4 at Level 1 and Corridor 1 at Level 2.

The package also includes 6.673 km of at-grade formation works, comprising embankments, cuttings, blanketing, minor and major infrastructure structures, retaining walls, drains, boundary walls, fencing and associated infrastructure.

An additional provision requires design validation and stability checks, wherever applicable, for works executed by the previous contractor.

The work location is the Jakkur–Rajanukunte section, excluding stations. Bids must be submitted by 3:30 PM IST on January 6, 2027.

Tender Submission Details

Bi-RIDE has specified separate submission deadlines for the two packages on the same date.

Package 3 closes at 3:00 PM IST, while Package 4 closes at 3:30 PM IST on January 6, 2027.

The tender notifications mark another procurement step in the development of Bengaluru's suburban rail network, with Corridor 4 involving both elevated and at-grade railway infrastructure.

Interested bidders can refer to the online tender portal for detailed tender documents, eligibility conditions and bid submission requirements.

  