Bangalore Metro: Project Information, Routes, Fares and other Details

Sangeeta Singh Posted on: 2022-01-31 12:29:00 Viewer: 3,567 Comments: 0 Country: India City: Bengaluru

Bangalore Metro: Project Information, Routes, Fares and other Details

In the bustling urban landscape of Bangalore, India, an ambitious transformation is underway with the development of an extensive metro rail network. With eight metro rail lines spanning a combined length of 254.85 kilometers, this transformative project is poised to revolutionize the city's transportation landscape. Backed by a substantial project cost of Rs. 62,453 INR, this metro rail endeavor is not only set to ease commuter congestion but also foster sustainable urban growth and connectivity for years to come. The metro train operation in the first Phase of the Bangalore Metro project was started on 20 October 2011 and the system is now covering a total of 79.05 km with two lines. By the end of 2027, the Bangalore Metro will cover a total network of 254.85 kilometers.

Project Summary

  • Project Name: Bangalore Metro Rail Project (Namma Metro)
  • Operator: Bangalore Metro Rail Corporation Limited
  • Owner: Govt. of India and Govt. of Karnataka
  • Project Type: Mass Rapid Transit System (MRTS)
  • No. of Phases: 3
  • Total Network Length: 254.85 km
  • Project Cost: Rs 62,453 crores
  • Funding: Govt. of Karnataka, Govt. of India, JICA, ADB, EIB, Infosys and Biocon
  • Status: Operational since October 20, 2011

Routes & Network

Line   Routes   Length   Status   Read More
#1 Purple   Benniganahalli-Kengeri   42.53km   Operational   Phase 1, Phase 2
#2 Green   Nagasandra-Yelachenahalli   36.52km   Operational   Phase 1, Phase 2
#3 Yellow   RV Road-Bommasandra   19.14km   U/C   Phase 2
#4 Pink    Kalena Agrahara-Nagawara   21.38km   U/C   Phase 2
#5 Blue    KR Puram-KIAL Terminals   55.23km   U/C   Phase 2
#6 Orange   JP Nagar 4th Phase- Kempapura   32.15km   Approved   Phase 3
#7 (TBA)   Hosahalli-Kadabagere     12.5km   Approved    Phase 3
#8 (TBA)   Hebbal-Sarjapur   35.4km   Approved   Phase 3

Operational Routes

Line 1 (Purple): Whitefield - Kengeri

  • Route Length: 39.34 km
  • No. of Stations: 35
  • Stations: Whitefield (Kadugodi), Hope Farm Channasandra, Kadugodi Tree Park, Pattandur Agrahara, Sri Sathya Sai Hospital, Nallur Halli, Kundanahalli, Seetharam Palya, Hoodi, GarudacharyaPalya, Singayyanapalya, Krishnarajapura (KR Pura), Baiyyappanahalli, Swami Vivekananda Road, Indiranagar, Halasuru, Trinity, Mahatma Gandhi Road, Cubbon Park, Vidhana Soudha, Sir M. Visveshwaraya, Majestic, City Railway Station, Magadi Road, Hosahalli, Vijayanagar, Attiguppe, Deepanjali Nagar, Mysuru Road, Nayandahalli, Rajarajeshwari Nagar, Jnana Bharathi, Pattanagere, Kengeri Bus Terminal and Kengeri.
  • Depot: Baiyyappanahalli and Kadugodi 

Line 2 (Green): Nagasandra - Silk Institute

  • Route Length: 30.32 km
  • No. of Stations: 29 
  • Stations: Nagasandra, Dasarahalli, Jalahalli, Peenya Industry, Peenya, Goraguntepalya, Yeshwanthpur, Sandal Soap Factory, Mahalakshmi, Rajajinagar, Kuvempu Road, Srirampura, Sampige Road, Majestic, Chickpet, Krishna Rajendra Market, National College, Lalbagh, Southend Circle, Jayanagar, Rashtriya Vidyalaya Road, Banashankari, Jayaprakash Nagar, Yelachenahalli, Konanakunte Cross, Doddakallasandra, Vajrahalli, Thalaghattapura and Silk Institute.
  • Depot: Peenya

Future expansion

Line 1 Extn (Purple): Baiyyappanahalli - Whitefield

  • Route Length: 1.54 km
  • No. of Stations: 1
  • Stations: Benniganahalli
  • Depot: Kadugodi 

Line 1 Extn (Purple): Kengeri - Challaghatta

  • Route Length: 1.314 km
  • No. of Stations: 1
  • Station: Challaghatta
  • Depot: Challaghatta

 Line 2 Extn (Green): Yelachenahalli - Silk Institute

  • Route Length: 6.2 km
  • No. of Stations: 5
  • Station: Doddakallasandra, Konankunte Cross, Vajrahalli, Thalgattapura and Silk Institute
  • Depot: Anjanapura

 Line-3 (Yellow): RV Road – Bommasandra

  • Length: 19.143 km
  • Type: Elevated
  • Number of Stations: 16
  • Station Names: Rashtreeya Vidyalaya Road, Ragigudda, Jayadeva Hospital, BTM Layout, Central Silkboard, Bommanahalli, Hongasandra, Kudlu Gate, Singasandra, Hosa Road, Beratena Agrahara, Electronic City, Infosys Foundation Konappana Agrahara, Huskur Road, Hebbagodi and Bommasandra
  • Depot: Hebbagodi Depot
Line-4 (Pink): Kalena Agaraha – Nagawara
  • Length: 21.386 km
  • Type: Elevated (7.501 km) and Underground (13.885 km) 
  • Number of Stations: 18
  • Station Names: Kalena Agrahara, Hulimavu, IIM-Bangalore, JP Nagar 4th Phase, Jayadeva Hospital, Swagath Road Cross, Dairy Circle, Lakkasandra, Langford Town, Rashtriya Military School, MG Road, Shivaji Nagar, Cantonment, Pottery Town, Tannery Road, Venkateshpura, Kadugundanahalli and Nagawara
  • Depot: Kothanur Depot 

Phase 2A 

Line-5 (Blue): KR Puram – Central  Silkboard

  • Length: 18.236 km
  • Type: Elevated
  • Number of Stations: 13
  • Station Names: KR Puram, Mahadevpura, DRDO Sports Complex, Doddanakundi, ISRO, Marathahalli, Kodibisanahalli, Kadubeesanahalli, Bellandur, Ibbalur, Agara Lake, HSR Layout, Silk Board.

Phase 2B

Line-5 Extn.(Blue): KR Puram – Hebbal – KIAL Terminals

  • Length: 37 km
  • Type: Elevated, At-Grade and Underground
  • Number of Stations: 17
  • Station Names: Kasturinagara, Horamavu, HRBR Layout,Kalyan Nagar, HBR layout, Nagawara, Veerannapalya, Kempapura, Hebbal, Kodigehalli, Jakkur Cross, Yelahanka,Bagalur Cross, Bettahalasuru, Doddajala,Airport City and KIAL Terminals
  • Depot: Shettigere Depot 

Line-6 (Orange) JP Nagar 4th Phase - Kempapura

  • Length: 32.15 km
  • Number of Stations: 22
  • Station Names: JP Nagar 4th Phase, JP Nagar 5th Phase, JP Nagar, Kadirenahalli, Kamakya Junction, Hosakerehalli, Dwaraka Nagar, Mysore Road, Nagarbhavi Circle, Vinayaka Layout, Papireddypalya, BDA Complex Nagarbhavi, Sumanahalli Cross, Chowdeshwari Nagar, Freedom Fighter’s Colony, Kanteerava Nagar, Peenya, Muthyala Nagar, BEL Circle, Nagashetty halli, Hebbal railway station and Kempapura.
  • Depot: NA

Line-7 Hosahalli - Kadabagere  

  • Length: 12.5 km
  • Number of Stations: 30 (18.60 km Elevated & 16.80 km Underground)
  • Station Names: Hosahalli, KHB Colony, Kamakshipalya, Sumanahalli Cross, Sunkadakatte, Herohalli, Byadarahalli, Kamath Layout, Kadabagere. It will integrate with Metro at the two stations of Hoshahalli and Sumanahalli Cross.
  • Depot: NA

Line-8 Hebbal – Sarjapur

  • Length: 35.40 km
  • Project Cost: Rs 15,000 crore
  • Number of Stations: 30 (18.60 km Elevated & 16.80 km Underground)
  • Station Names: Hebbal, Veterinary College, Gangenahalli, Mekri Circle, Palace, Guttahalli, Cunningham Road, Basaveshwara Circle, Central College, Town Hall, Wilson Garden, Nimhans, Dairy Circle, Sudduguntepalya Koraman, St.Johns Hospital, Gala, Jakkasandra, Agara, Ibbalur, Bellandur Gate, Kaikondrahalli, Doddakanalli Gate, Carmelaram, Ambedkar Nagar, Kodati, Sulikunte, Muthanallur Cross, Dommasandra Circle, Sompura and Sarjapur.
  • Depot: NA

 Train Maintanance Depot

SNo. Phase  Line Location
1 Phase I Line 1 (Purple) Baiyappanahalli (Operational)
2 Phase I Line 2 (Green) Peenya (Operational)
3 Phase II Line (Yellow) Hebbagodi (Under Construction)
4 Phase II Line 3 (Green) 

Kothanur (Under Construction)

Fare 

Click here to check Bangalore Metro Route Fare

Banaglore Metro Route Map

Click to view on Google Maps

Key Dates

  • 25 April 2006: Phase 1 of the Bangalore Metro project was approved by Govt of India.
  • 24 June 2006: Foundation stone laid down by former Prime Minister Dr. Manmohan Singh.
  • 15 April 2007: Construction work on Phase I started.
  • 20 October 2011: 6.7 km section (Baiyyappanahalli – MG Road) of Line 1 (Purple) opened.
  • 1 March 2014: 5.1 km section (Sampige Road - Yeshwanthpura) of Line 2 (Green) opened.
  • 1 March 2014: 4.8 km section (Yeshwanthpura - Peenya Industry) of Line 2 (Green) opened.
  • 1 May 2015: 2.5 km section (Peenya Industry - Nagasandra) of Line 2 (Green) opened.
  • 16 November 2015: 6.4 km sectio (Mysuru Road - Magadi Road) Line 1 (Purple) opened.
  • 30 April 2016: 4.8 km section (Mahatma Gandhi - Magadi Road)  of Line 1 (Purple) opened.
  • 18 June 2017: 4.0 km section (Sampige Road - National College) of Line 2 (Green) opened.
  • 18 June 2017: 6.4 km section (National College - Yelachenahalli) of Line 2 (Green) opened.
  • 15 January 2021: 6.3 km section (Yelachenahalli - Silk Institute) of Line 2 (Green) opened.
  • 30 August 2021: 7.5 km section (Mysuru Road - Kengeri) of Line 1 (Purple) opened.
  • 25 March 2023: 13.71 km section (KR Pura - Whitefield) of Line 1 (Purple) opened.

Helpline 

1800-425-12345, 80- 2296 9300, 2296 9301.

Operator

Bangalore Metro Rail Corporation Limited

III Floor, BMTC Complex, K.H.Road,

Shanthinagar, Bangalore 560027

Email: travelhelp@bmrc.co.in

Website: www.bmrc.co.in 

  