Surat Metro sets new deadlines to launch Phase 1 corridors in Diamond City

Vinod Shah Posted on: 2023-08-18 07:00:00 Viewer: 9,564 Comments: 0 Country: India City:

Surat Metro sets new deadlines to launch Phase 1 corridors in Diamond City

Surat, India (Metro Rail Today): In the heart of Gujarat lies the bustling city of Surat, where a transformative journey is underway – the construction of the Surat Metro. With each milestone achieved, the city inches closer to a modern, efficient, and interconnected urban transport system that will reshape the way its residents commute. Let's delve into the latest updates and the exciting future that the Surat Metro holds.

Progress in Motion: Viaduct Milestone

A significant stride has been made in the construction of the Surat Metro, with a remarkable 466 meters of viaduct completed. This architectural feat is a testament to the dedicated efforts and expertise of the teams involved. As this section of the viaduct reaches completion, the anticipation for the next phase builds, bringing the city closer to a seamlessly connected metro network.

Paving the Way: Next Steps in Track Laying

As the completed viaduct stands tall, the next phase in the Surat Metro journey is set to commence – track laying. This crucial step will come into action after the first kilometer of the viaduct is accomplished. With precision and meticulous planning, the tracks will be laid, forming the intricate web that will allow the Surat Metro to glide smoothly across the cityscape.

New Deadlines Set for Achievement

The Surat Metro project is not only making strides but is also driven by ambitious deadlines. Line-1, spanning a combined length of 18 kilometers (11 km elevated + 7 km underground), connecting Dream City to Kapodra, is set to become operational by December 2024. The momentum doesn't stop there. Another segment of Line-1, covering 4 kilometers of elevated track from Kapodra to Sarthana, is projected to be completed by March 2025. Meanwhile, Line-2, stretching over 19 kilometers in an elevated configuration from Bhesan to Saroli, is also targeted for completion by March 2025. These deadlines are a testament to the commitment to progress and the vision of creating an efficient transport system for the city.

Unveiling the Surat Metro: A Glimpse into the Future

The Surat Metro Rail project encompasses two corridors, spanning a total length of 40.35 kilometers. These corridors will intertwine and connect various parts of the city, facilitating swift and convenient movement for its residents. With construction underway since January 18, 2021, the project is projected to reach completion by December 2027. The estimated cost of this transformative endeavor is Rs 12,020.32 crore, a testament to the significant investment being made to enhance urban mobility and connectivity.

As the Surat Metro takes shape, it symbolizes a future where commuting is not just a necessity but a seamless experience that brings the city closer together. This ambitious project is a testament to the city's commitment to progress, efficiency, and a better quality of life for its citizens. With the cityscape poised to evolve, Surat is gearing up to embrace a new era of connectivity, accessibility, and growth.

  