Assam Govt Cabinet approves four-phase Guwahati Metro Rail Project with ₹18,000 crore Investment
RITES awarded DPR Contract for 55-km Nagpur Metro Phase 3 Expansion with Four New Corridors
Mumbai Metro One secures ₹2,771 crore Debt Restructuring, Insolvency proceedings set to end
TBM Durga achieves major tunnel breakthrough at Victoria for Kolkata Metro Purple Line Expansion
UPMRC floats ₹670 Crore Rolling Stock Tender for 45 Metro Cars for Lucknow Metro Phase 1B
Maha Metro launches ₹994.78 crore Rolling Stock Tender for Nagpur and Pune Metro Phase 2
Afcons Infrastructure wins ₹1,045 crore Civil Contract for Ramwadi–Wagholi Metro Corridor in Pune
6th RailTrans Expo 2026 concludes on a Grand Note, Reinforcing India's Vision for Viksit Rail 2047
Keralam High-Speed Rail proposal is technically feasible but project cost may double: Expert Panel
DMRC begins Construction work on Inderlok–Indraprastha Corridor under Delhi Metro Phase 4 Expansion
New Delhi, India (Metro Rail Today): The Delhi Metro Rail Corporation (DMRC) has announced major progress in its ongoing Phase 4 expansion, with approximately 70% of construction completed on several critical metro corridors connecting Chhatarpur Mandir, IGNOU, Kishangarh, and Vasant Kunj. The announcement underscores DMRC’s continued commitment to enhancing public transportation infrastructure in Delhi.
Among the key updates, DMRC confirmed that a 4.6-kilometre stretch between Majlis Park and Jagatpur Village is close to completion. This section includes three upcoming metro stations Burari, Jharoda Majra and Jagatpur Village.
Trial runs on this route commenced in December 2024, and the segment is expected to open to the public once all statutory approvals and safety certifications are obtained.
Significant construction milestones were also achieved on the Aerocity–Tughlakabad corridor, where three major tunnel breakthroughs have been successfully completed over the past two months. This corridor is a vital link in Phase 4, aimed at improving connectivity in South Delhi and adjoining areas.
Earlier this year, on January 5, 2025, the Janakpuri West–Krishna Park Extension—the first operational section of Phase 4—was inaugurated, marking a key milestone in the project. On the same day, the foundation stone for the Rithala–Kundli corridor was laid, further signaling DMRC’s intent to expand Delhi’s metro reach into neighboring regions.
With over 112 kilometres of new metro lines under development as part of Phase 4, DMRC is poised to significantly boost last-mile connectivity and reduce traffic congestion across the National Capital Region. Once completed, the expansion will serve millions of commuters, making daily travel faster, safer, and more efficient.
Key Highlights:
70% completion of metro lines connecting Chhatarpur Mandir, IGNOU, Kishangarh & Vasant Kunj
4.6-km stretch from Majlis Park to Jagatpur Village nearing readiness
Three new stations: Burari, Jharoda Majra, Jagatpur Village
Trial runs underway since December 2024
Three tunnel breakthroughs on the Aerocity–Tughlakabad corridor
Janakpuri West–Krishna Park Extension opened to public in January 2025
Rithala–Kundli corridor foundation laid
DMRC’s strategic efforts in urban mobility enhancement are aligned with Delhi’s growing population and transport demands, aiming to create a world-class metro network that integrates underserved areas and ensures seamless commuting.