NMRC invites Applications for Key Executive Positions for Noida Metro Rail Project
Central Govt rejects revised DPR of 7.5 km Noida-Greater Noida Metro Rail Extension Project
Revised DPR of Prayagraj Metro focuses on seamless Rail-Air connectivity
DMRC floats Tender for Central Vista Depot Design in Delhi Metro Phase V Expansion
MMRDA seeks ₹14,100 Crore Loan for two upcoming Mumbai Metro Corridors
Jupiter Wagons Eyes ₹20,000-Crore Mumbai Suburban Mega Rolling Stock Tender
Mumbai Metro Chief Ashwini Bhide appointed as First Woman BMC Commissioner
TBM ‘Parvati’ completes Underground Tunnelling on Kanpur Metro Phase 1 Project
Surat Metro begins First Trial Run on 8.5 km Diamond Corridor between Dream City and Althan Tenement
Cemindia wins ₹1,024 crore Civil Contract for Central Vista Tunnel Package of Delhi Metro Phase V
New Delhi, India (Metro Rail Today): The Delhi Metro Rail Corporation (DMRC) has announced major progress in its ongoing Phase 4 expansion, with approximately 70% of construction completed on several critical metro corridors connecting Chhatarpur Mandir, IGNOU, Kishangarh, and Vasant Kunj. The announcement underscores DMRC’s continued commitment to enhancing public transportation infrastructure in Delhi.
Among the key updates, DMRC confirmed that a 4.6-kilometre stretch between Majlis Park and Jagatpur Village is close to completion. This section includes three upcoming metro stations Burari, Jharoda Majra and Jagatpur Village.
Trial runs on this route commenced in December 2024, and the segment is expected to open to the public once all statutory approvals and safety certifications are obtained.
Significant construction milestones were also achieved on the Aerocity–Tughlakabad corridor, where three major tunnel breakthroughs have been successfully completed over the past two months. This corridor is a vital link in Phase 4, aimed at improving connectivity in South Delhi and adjoining areas.
Earlier this year, on January 5, 2025, the Janakpuri West–Krishna Park Extension—the first operational section of Phase 4—was inaugurated, marking a key milestone in the project. On the same day, the foundation stone for the Rithala–Kundli corridor was laid, further signaling DMRC’s intent to expand Delhi’s metro reach into neighboring regions.
With over 112 kilometres of new metro lines under development as part of Phase 4, DMRC is poised to significantly boost last-mile connectivity and reduce traffic congestion across the National Capital Region. Once completed, the expansion will serve millions of commuters, making daily travel faster, safer, and more efficient.
Key Highlights:
70% completion of metro lines connecting Chhatarpur Mandir, IGNOU, Kishangarh & Vasant Kunj
4.6-km stretch from Majlis Park to Jagatpur Village nearing readiness
Three new stations: Burari, Jharoda Majra, Jagatpur Village
Trial runs underway since December 2024
Three tunnel breakthroughs on the Aerocity–Tughlakabad corridor
Janakpuri West–Krishna Park Extension opened to public in January 2025
Rithala–Kundli corridor foundation laid
DMRC’s strategic efforts in urban mobility enhancement are aligned with Delhi’s growing population and transport demands, aiming to create a world-class metro network that integrates underserved areas and ensures seamless commuting.