Siemens Bags Order from Titagarh Rail Systems for Pune Metro Extension Trainsets
Titagarh Rail Systems becomes Corporate Member of Chamber of Railway Industries (Rail Chamber)
World Bank approves ₹1,400 crore Civil Tender for Gurugram Metro Phase 2
Bi-RIDE invites ₹200 crore Tender for Soladevanahalli Depot of Bengaluru Suburban Rail Project
GHV India awarded ₹107.79 crore Civil Contract for Lucknow Metro East-West Corridor
Pune Metro Line 3 set to launch First 12-km Section on 15 July 2026
DMRC gets approval to Fell or Transplant 364 Trees for Central Vista Metro Corridor under Phase IV
₹4.5 Lakh crore Metro Rail Investment reaches less than 5% of Urban Population in India
West Bengal plans to launch Water Metro Systems in Kolkata
Titagarh Rail Systems targets full Indigenous Aluminium Coach Manufacturing by FY2027
(Image for representative purpose only)
New Delhi, India (Metro Rail Today): The Delhi Metro Rail Corporation Limited (DMRC) today opened the revised financial bids for the civil contract (underground tunneling) package DC-09 of Phase 4 of the Delhi Metro Rail Project.
As per information shared by DMRC, Larsen & Toubro Ltd (L&T) emerged as the lowest bidder for the construction of the 6.51 km tunnel between Chhattarpur and Neb Sarai Stations of the 23.622 km Aerocity to Tughlakabad Corridor (Silver Line) that comprises of 4 stations at Chhattarpur, Chhattarpur Mandir, IGNOU and Neb Sarai.
Afcons Infrastructure Ltd was the lowest bidder for this contract package but it had quoted Rs 1,779 crore which was significantly higher than the DMRC’s estimate of Rs 1,427.87 crores. Hence, DMRC called a revised quotation from all qualified bidders.
The original & revised financial position of each bidder is as under:-
| Bidder | Original Bid Value | Revised Bid Value |
| Larsen & Toubro Ltd | Rs 2,610 crore (L4) | Rs 1,737.22 crore (L1) |
| Afcons Infrastructure Ltd | Rs 1,779 crore (L1) | Rs 1,739.64 crore (L2) |
| Gülermak Ağır Sanayi İnşaat ve Taahhüt A Ş. | Rs 2,329 crore (L3) | Rs 1,940.90 crore (L3) |
| ITD Cementation India Ltd | Rs 2,029 crore (L2) | Rs 2,028.40 crore (L4) |
(DMRC's Estimate: Rs 1,427.87 crore)
The scope of work includes Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box, Underground Ramp and four Underground stations namely Chhattarpur, Chhattarpur Mandir, IGNOU and Neb Sarai with Entry/Exits & Connecting subways from chainage 5356.285 mtr. to 11867.000 mtr. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi Metro Rail Project.
Now all bids have been sent for final evaluation.
The 23.622 km long Silver Line of Delhi Metro will connect Delhi Aerocity to Tughlakabad through 15 stations. This line is scheduled to open for public by the end of 2025.
For more details, please explore the Delhi Metro page of Metro Rail Today.