The Greater Noida Industrial Development Authority on 4 December 2018, approved the Noida Metro Phase 2 from Noida Sector 51 to Knowledge Park V in Greater Noida. The extension will cover up to 15 km and comprise 9 stations and cost Rs 2602 crore.
Project Summary
- Project Name: Noida Metro Rail Project
- Operator: Noida Metro Rail Corporation Limited
- Owner: Govt. of India and Govt. of Uttar Pradesh
- Project Type: Mass Rapid Transit System (MRTS)
- Project Cost: INR 5,503 Crore (Phase-I)
- Total Planned Metro Network: 49.64 km
- Operational Network: 29.7 km (1 Line, 22 Stations)
Project Information Phase-II
Line 1 Extension (Aqua Line): Noida Sec 71 - Knowledge Park V
- Project Cost: Rs 2,682 crore
- Route Length: 14.958 km
- Total Stations: 9
- Station Names: Sector 122, Sector 123, Sector 4, Ecotech 12, Sector 2, Sector 3, Sector 10, Sector 12 and Knowledge Park V
- Interchange Stations: Sector-71 (Aqua Line)
- Status: Approved
- Deadline: 2022
Line 2: Noida Sector 142 - Botanical Garden
- Project Cost: Rs 3,000 crore
- Route Length: 14 km
- Total Stations: 10
- Station Names: Sector 142, Sector 136, Sector 91, Sector 93, Sector 98, Sector 127, Sector 97, Sector 126, Sector 125, Sector 94.
- Interchange Stations: Botanical Garden
- Status: Proposed
New Line – Greater Noida Knowledge Park II – Jewar Airport
- Length: 35.64 km
- Total Stations: 25
- Station Names: Greater Noida’s Knowledge Park-II, Chi-I, Chi-II, Chi-III, Chi-IV, Gautam Budh University, Night Safari, Murshadpur, Yamuna Authority’s Sector 26A, Noida International University, Galgotia University, Sector 17A, Sports City, Sector 22A, Sector 22B, Sector 18A, Sector 22C, Sector 19, Sector 2, Sector 20, Sector 21, Sector 28, Sector 29, Nagla Hukum Singh and Jewar Airport
Technical Information
- Design Speed: 200 kmph
- Average speed: 160 kmph
- Track Gauge: Broad Gauge
- Electrification: NA
- Signalling System: Communications-based Train Control (CBTC)
- Rolling stock: NA
Major Contracts
NA
Progress So Far
- Dec 2018: Uttar Pradesh government approved the project on 04-Dec-2018
- Dec 2019: Project approved in Uttar Pradesh cabinet meeting, project deadline set to 2022
- Jun 2020: Tenders invited and to be submitted by end of June-2020.
- July 2020: Tender for construction to be awarded by September.
In-depth Information