T&T Infra–Univastu JV Bags ₹229.97 Crore Civil Contract of Pune Metro Rail Project
Rail composites market set to reach $2.4 billion by 2028 as Railways embrace lightweight materials
Alstom powers Delhi Metro's Pink and Magenta Line with Driverless Trains and CBTC Signalling
South India's 744-km Chennai–Hyderabad Bullet Train Corridor set to transform connectivity
TDC Contracting bags ₹92.10 Crore E&M Systems Contract for Chennai Metro Phase 2 Corridor 3
Bids Invited for 5-Year Rolling Stock Maintenance Contract for Navi Mumbai Metro Line 1
Madhya Pradesh plans to expand Indore Metro to Ujjain, Pithampur and Mhow
Punjab approves 27-km long Pakistan’s first fully underground Lahore Blue Line Metro Project
Tec4 Ingenieros-led JV appointed as Independent Engineer for ₹1,016 Crore BKC Pod Taxi Project
MMRDA to appoint General Consultant for ₹4,063 Crore Mumbai Metro Line 5A Extension
Chennai, India (Metro Rail Today): Chennai Metro Rail Limited (CMRL) has reached another major milestone under Phase-2 with the second Tunnel Boring Machine (TBM) under the UG-01 contract completing its breakthrough at the Thirumayilai shaft on Corridor-4.
The downline TBM, Flamingo S-1352A, achieved breakthrough at the Thirumayilai station site on 27 February, successfully completing the 1,985-metre tunnel drive between Light House and Thirumayilai. This follows the earlier breakthrough of the upline tunnel by TBM Eagle S-1073B on 9 February, marking the completion of both parallel tunnels on this stretch.
The tunnelling works were executed by Cemindia Projects Limited and involved navigating beneath some of Chennai’s most sensitive and densely built areas. The alignment passed under the Lighthouse precinct, All India Radio campus, Russian Embassy zone, Rosary Church, MRTS bridge and Buckingham Canal, along with other heritage and high-importance structures.
The drive presented significant engineering challenges, including rocky strata, shallow overburden sections, deeper overburden due to stacked tunnel configuration, and the presence of unforeseen gas pockets. A particularly complex segment involved a stacked tunnel “drive-through” beneath Kutcheri Road before reaching Thirumayilai. The tunnel depth at Thirumayilai is approximately 28 metres, making it the deepest underground station in Phase-2.
Thirumayilai is also a critical interchange point where Corridor-4 intersects with Corridor-3, enhancing its strategic importance within the network.
With the successful breakthrough of TBM Flamingo, both TBMs deployed for this section—Eagle and Flamingo—have completed their respective drives under the UG-01 package. The completion of twin tunnelling works significantly de-risks the underground construction phase for this stretch of Corridor-4.
Commenting on the achievement, Mrs. Mamta Shah, MD & CEO, Urban Infra Group, said, “Executing deep, stacked tunnelling beneath heritage and high-security zones is a complex engineering feat. The successful completion of both tunnel drives between Light House and Thirumayilai reflects the technical capability and meticulous planning that underpin Chennai Metro’s Phase-2 expansion.”
The milestone reinforces steady progress on Corridor-4, bringing Chennai closer to expanding its underground metro network and strengthening multimodal urban connectivity.