Know all about current progress of Mumbai Metro Rail Project

Surya Shah Posted on: 2023-08-04 09:19:00 Viewer: 2,613 Comments: 0 Country: India City: Mumbai

Know all about current progress of Mumbai Metro Rail Project (Representative Image)

In a significant stride towards enhancing Mumbai's urban transport network, the Mumbai Metro Rail Project has been steadily advancing. The project, aimed at alleviating the city's ever-growing commuting challenges, is witnessing notable developments across various lines. Here's a glimpse into the current status of key lines as of August 1, 2023:

 

Operational Lines:

  • Line 1 - Blue Line (Versova - Ghatkopar, 11.4km): Successfully operational, providing a crucial link between eastern and western suburbs.

  • Line 2A - Yellow Line (Dahisar East - D.N. Nagar, 18.5km): Now operational, facilitating seamless connectivity along its route.

  • Line 7 - Red Line (Dahisar East - Gundavali, 16.49km): Operating efficiently, serving commuters effectively within its designated corridor.

Under Construction Lines:

  • Line 2B - Yellow Line (D.N. Nagar - Mandale, 23.643km): Progressing well, with completion currently at 42%, promising enhanced accessibility.

  • Line 3 - Aqua Line (Cuffe Parade - SEEPZ - Aarey Colony, 35.9 km): Rapidly advancing at 85% completion, poised to become a vital link across the city.

  • Line 4 - Green Line (Wadala - Kasarvadavali, 32.32km): Making headway at 61%, expected to significantly decongest key routes upon completion.

  • Line 4A - Green Line (Kasarvadavali - Gaimukh, 2.7km): Progressing steadily at 42%, catering to increasing transportation needs.

  • Line 5 - Orange Line (Thane - Kalyan, 24.9km): Remarkably reaching 82% completion between Thane - Bhiwandi and the remaining space between Bhiwandi - Kalyan is proposed.

  • Line 6 - Pink Line (Lokhandwala Swami Samarth Nagar - Kanjurmarg, 14.47km): Advancing well at 70%, contributing to enhanced connectivity.

  • Line 7A - Red Line (Line 7 Extension to CSIA, 3.17km): Currently 14% completed, extending connectivity to Chhatrapati Shivaji International Airport.

  • Line 9 - Red Line (Line 7 Extension to Mira Bhayander, 10.41km): Making steady progress at 55%, addressing crucial suburban links.

  • Line 10 - Green Line (Line 4 Extension to Mira Road, 9.209km): With PMC appointed, further expansion is underway.

Upcoming and Planned Extensions:

  • Line 8 - Gold Line (CSIA - NMIA, 35km): Currently at the DPR stage, poised to offer seamless airport connectivity.

  • Line 11 - Green Line (Line 4 Extension to CSMT Station12.774km): In the DPR stage, envisioned to streamline connectivity to Chhatrapati Shivaji Maharaj Terminus.

  • Line 12 - Orange Line (Line 5 Extension to Taloja, 20.756): Inviting bids again after necessary revisions, aiming to cater to expanding needs.

  • Line 13 - Purple Line (Mira Road - Virar, 23km): In the DPR stage, contributing to extended connectivity.

  • Line 14 - Magenta Line (Vikhroli - Badlapur, 45km): Under DPR stage, gearing up for future expansion.

The Mumbai Metro Rail Project continues to reshape the city's transportation landscape, ushering in convenience, efficiency, and enhanced connectivity for millions. As these lines near completion and new extensions take shape, Mumbai's vision for a robust urban transit network moves ever closer to realization.