MMRDA updates current status of all metro rail corridors in Mumbai Metropolitan Region

MRT Online Desk Posted on: 2024-08-19 08:30:00 Viewer: 6,021 Comments: 0 Country: India City: Mumbai

MMRDA updates current status of all metro rail corridors in Mumbai Metropolitan Region

Mumbai, India (Metro Rail Today): Mumbai, one of India's most bustling metropolitan areas, is witnessing a transformative phase in its transportation infrastructure with the development of an extensive metro network. The Mumbai Metropolitan Region (MMR) is set to benefit from a robust metro system that aims to revolutionize urban mobility and connectivity. Currently, 14 metro lines are being developed, covering a total of 337.1 kilometers, which will serve as the backbone of the city's public transportation system.

Operational Metro Lines

Mumbai's metro network has already made significant strides with several lines fully operational, providing a glimpse into the future of urban transportation in the city:

  • Line 1: Versova-Andheri-Ghatkopar Line
    This inaugural line, stretching 11.4 kilometers, has been operational since June 8, 2014. It connects key areas from Versova to Ghatkopar, facilitating smoother commutes across this vital corridor.

  • Line 2A: Dahisar (E)-D.N. Nagar Line
    Covering 18.6 kilometers, Line 2A was launched in two phases: Phase I became operational on April 2, 2022, followed by Phase II on January 19, 2023. This line provides essential connectivity from Dahisar to D.N. Nagar.

  • Line 7: Andheri (E)-Dahisar (E) Line
    Running parallel to Line 2A, this 16.5-kilometer line also commenced operations in phases, with Phase I starting on April 2, 2022, and Phase II on January 19, 2023.

Metro Lines Under Construction

The development of additional metro lines is underway, with eight lines currently under construction. These lines collectively cover 165.7 kilometers, reflecting a significant expansion of the metro network:

  • Line 2B: D.N. Nagar-Mandale
    Spanning 23.6 kilometers, Line 2B is progressing with 70.7% of civil work completed. The track work and architectural finishes are advancing, especially between Mandale and Chembur. The depot work at Mandale is also nearing completion.

  • Line 4: Wadala-Kasarvadavali
    This 32.3-kilometer line has seen 70.13% of civil work completion. Architectural finishes and track installation for 17 kilometers are ongoing. The contractor for the Mogharpada Depot’s civil work has been appointed.

  • Line 4A: Kasarvadavali-Gaimukh
    The 2.7-kilometer extension of Line 4, known as Line 4A, has achieved 74.58% completion in its civil work.

  • Line 5: Thane-Bhiwandi-Kalyan
    Covering 24.9 kilometers, Line 5’s Phase I (Thane-Bhiwandi) has 89.9% of its civil work completed. Civil and track installation works are in progress, with the Kasheli Depot’s civil work awarded.

  • Line 6: Swami Samarthnagar-Vikhroli
    The 14.5-kilometer Line 6 has seen 75.7% of its civil work completed, with ongoing construction of the depot at Kanjurmarg.

  • Lines 7A & 9: Dahisar (E)-Mira Bhayander & Andheri (E)-CSMIA
    Line 9, covering 13.5 kilometers, is 86.4% completed, while Line 7A stands at 37% completion.

  • Line 12: Kalyan-Taloja
    This 20.7-kilometer line has recently commenced civil work.

  • Line 3: Colaba-Bandra-Seepz
    The extensive 33.5-kilometer Line 3 is under construction by MMRCL, reflecting a major advancement in the metro network.

Lines in Tendering Process

Two additional metro lines are currently in the tendering phase, with detailed project reports (DPRs) being prepared for several more:

  • Line 10: Gaimukh-Shivaji Chowk (Mira Road)
    This 9.2-kilometer line is under evaluation for alignment and technical feasibility.

  • Line 11: Wadala-CSMT
    Covering 12.7 kilometers, this project has been handed over to MMRCL. Preparations are underway for DPRs for three further metro lines.

Upcoming Metro Lines

  • Line 8: Airport Road (CSMIA-NMIA)
    Spanning 35 kilometers, this line’s DPR will be prepared by CIDCO, with the implementation expected to follow a public-private partnership model.

  • Line 13: Shivaji Chowk (Mira Road)-Virar
    This 23-kilometer line’s DPR is nearing finalization.

  • Line 14: Kanjurmarg-Badlapur
    The 45-kilometer line’s draft DPR has been received from Milan Metro.

Mumbai’s metro expansion is a testament to the city’s commitment to improving urban mobility and infrastructure. With multiple lines either operational, under construction, or in the planning stages, the Mumbai Metropolitan Region is set to experience a significant transformation in connectivity. This extensive network will not only alleviate traffic congestion but also provide a sustainable and efficient mode of transportation, supporting Mumbai’s growth and development in the coming years.

  