Rail Chamber submits key recommendations to Railway Ministry for Budget 2026-27
Hyderabad Metro at Crossroads: Operational Excellence, Financial Realities and the Future of PPPs
Kalpataru Projects wins ₹451 crore Third Rail Electrification Contract for Kochi Metro Phase 2
ABB bags driverless traction propulsion contract for Mumbai Metro Lines 5 & 6
Govt of India approves ₹35,000 crore Delhi-Bawal Namo Bharat RRTS Corridor
Maharashtra Govt approves 35-km Mumbai-Navi Mumbai Gold Line Metro Project
Vijayawada Metro at crossroads due to funding uncertainty and political doubts
Bhopal Metro in trouble, faces Low Ridership, Rising Costs Issues
Global Urban Rail Transit market projected to reach USD 265.84 billion by 2033
Centre approves Kerala High-Speed Rail Corridor; ‘Metro Man’ Sreedharan to steer DPR, DMRC entrusted
Kolkata, India (Metro Rail Today): Titagarh Rail Systems Limited (TRSL), a leading Indian manufacturer of rolling stock, has initiated the production of trainsets for the Bangalore Metro Rail Corporation Limited's (BMRCL) Phase 2 Yellow Line project. This development marks a significant milestone in Titagarh's contribution to India's urban transportation infrastructure.
The contract between BMRCL and China Railway Rolling Stock Corporation (CRRC) Nanjing Puzhen Co Ltd, signed in December 2019, faced challenges that resulted in delays beyond the original deadlines. To mitigate these delays in rolling stock supply, CRRC entered into a Memorandum of Understanding (MoU) with Titagarh Rail Systems. Under this agreement, Titagarh will manufacture the majority of the trainsets required for the Yellow Line project at its advanced facility in Uttarpara.
Titagarh is tasked with producing 34 out of the 36 trainsets needed for the Yellow Line project, with only two trainsets (comprising 12 coaches) being manufactured in China. To meet the project's specific requirements, Titagarh has set up a dedicated stainless steel production line at its Uttarpara facility. Production commenced on May 18th, 2024, and the first trainset is scheduled for delivery in August 2024.
The Yellow Line, spanning 21 kilometers from RV Road to Bommasandra, is a critical metro corridor designed to enhance connectivity and alleviate traffic congestion in Bengaluru. Once operational, this line is expected to significantly improve urban mobility for the city's residents, easing daily commute challenges.
Titagarh's involvement in this prestigious project underscores its commitment to supporting national infrastructure development through reliable transportation solutions. The company's extensive manufacturing capabilities enable it to cater to diverse transportation needs, solidifying its position as a leader in the rail transportation sector.
Titagarh Rail Systems Limited's commencement of trainset production for Bengaluru Metro's Yellow Line represents a pivotal step forward in the expansion of urban transit infrastructure in India. With its dedication to quality, innovation, and technological advancement, Titagarh continues to play a crucial role in advancing the country's transportation network.