STUP Consultants–Assystem JV wins ₹14.20 crore Design Consultancy for Ahmedabad Metro
Three Global Firms bid for General Consultancy Contract of Lucknow Metro Phase 1B Project
ETA Engg - PISCESIA JV awarded ₹225.87 crore E&M Contract for Delhi Metro Phase 5A Project
Mumbai–Ahmedabad Bullet Train cost rises to ₹2.03 Lakh crore; ₹92,761 crore spent by March 2026
Global Rail & Metro Infrastructure Market to Reach USD 462.13 Billion by 2033
Malaysia awards RM2.69 billion contract for Penang Mutiara Line’s Cross-Sea LRT Extension
Afcons Infrastructure wins ₹876.51 crore contract for Pune Metro Viaduct and Elevated Road Project
SYSTRA–led JV wins ₹228.78 crore Design Consultancy Contract for two 350 kmph Bullet Train Corridors
Paras Railtech wins ₹84.72 crore Ballastless Track Contract for Jaipur Metro Phase 1C Project
SYSTRA India wins DPR Consultancy Contract for Chennai Metro Phase II Corridor 5 Extension
Gurugram, India (Metro Rail Today): The Haryana Rail Infrastructure Development Corporation (HRIDC) has opened the technical bids for the first tunnel construction package (C-4) of the 121.7 km Haryana Orbital Rail Corridor (HORC) Project on 17th February 2023.
As per information shared by HRIDC, the six firms have submitted their bids to construct 4.7 km tunnel for Haryana Orbital Rail Corridor. The names of these firms are:
The scope of work includes under Package C-4:
i) Design & Construction of Twin Tunnel using NATM and Cut & Cover method from km 24.880 to km 29.580;
ii) Design & Installation of Ballastless Track (excluding supply of rails) from km 24.856 to km 29.680;
iii) Detailed Design, Supply, Installation, Testing & Commissioning of General Electrical Services including Supply, Erection, Testing and Commissioning of 11kV HT/LT Power and Control Cable Network, GIS Substation (11/0.433) kVA, Tunnel lighting system, etc. from km 24.880 to km 29.680;
iv) Design & Construction of Embankment, Bridges and other miscellaneous works from km 12.00 to km 18.00. Now all bids have been sent for technical evaluation.
In May 2022, HRIDC had awarded the first civil contract (Package C1) to KEC Buildcon Private Limited for the construction of 5.9 km priority section (Manesar-Patli Station) of Haryana Orbital Rail Corridor Project.
In October 2022, Union Home Minister Amit Shah had laid the foundation stone of Haryana Orbital Rail Corridor. The estimated cost of this project is Rs 5,618.00 crore.
For more details, please explore Haryana Orbital Rail Corridor page of Metro Rail Today.