Efkon India wins ₹103 crore Telecom Contract for Mumbai Metro Line 7A and 9
SYSTRA appointed Design Consultant for Patna Metro Underground Corridors
Kochi Metro Phase 2 Pink Line likely to miss June deadline due to funding issue
Saudi Arabia restarted work on Jeddah Metro Rail Project under Saudi Vision 2030
Delhi Govt releases funds for remaining Delhi Metro Phase IV Corridors
Italcertifer SpA appointed ISA for Mumbai-Ahmedabad High Speed Bullet Train Project
Univastu India Bags ₹391.76 Crore E&M Contract for Mumbai Metro Line 4 & 4A
Prime Minister Narendra Modi Flags Off India's First Vande Bharat Sleeper Train
Ceigall - SAM India JV Wins ₹918 Crore Civil Contract for Jaipur Metro Phase 2
Webuild Bags €776 Million Contract for Rome Metro Line C Section T1
Gurugram, India (Metro Rail Today): The Haryana Rail Infrastructure Development Corporation (HRIDC) has opened the technical bids for the first tunnel construction package (C-4) of the 121.7 km Haryana Orbital Rail Corridor (HORC) Project on 17th February 2023.
As per information shared by HRIDC, the six firms have submitted their bids to construct 4.7 km tunnel for Haryana Orbital Rail Corridor. The names of these firms are:
The scope of work includes under Package C-4:
i) Design & Construction of Twin Tunnel using NATM and Cut & Cover method from km 24.880 to km 29.580;
ii) Design & Installation of Ballastless Track (excluding supply of rails) from km 24.856 to km 29.680;
iii) Detailed Design, Supply, Installation, Testing & Commissioning of General Electrical Services including Supply, Erection, Testing and Commissioning of 11kV HT/LT Power and Control Cable Network, GIS Substation (11/0.433) kVA, Tunnel lighting system, etc. from km 24.880 to km 29.680;
iv) Design & Construction of Embankment, Bridges and other miscellaneous works from km 12.00 to km 18.00. Now all bids have been sent for technical evaluation.
In May 2022, HRIDC had awarded the first civil contract (Package C1) to KEC Buildcon Private Limited for the construction of 5.9 km priority section (Manesar-Patli Station) of Haryana Orbital Rail Corridor Project.
In October 2022, Union Home Minister Amit Shah had laid the foundation stone of Haryana Orbital Rail Corridor. The estimated cost of this project is Rs 5,618.00 crore.
For more details, please explore Haryana Orbital Rail Corridor page of Metro Rail Today.