The union government approved the project on 11 March 2019.It will be implemented by Gujarat Metro Rail Corporation Limited and it will be financed mainly through equity from Government of India and Government of Gujarat on 50:50 basis and loan from bilateral/ multilateral agencies.AFD has committed to lend 250 million euros for the project, which was signed on January 28, 2021
Click here to see station names, fare and route maps.
Phase | Project Cost | Funding By | ||
Phase-I | ₹12,020 Crore | Govt. of India, Govt. of Gujrat |
Package | Contractors | Work Description | ||
GEC | SYSTRA – AECOM – Egis Rail JV | Phase 1 General Engineering Consultant | ||
DDC | DIMMTS – Tec-Cuatro – NPEC Consultancy JV | Detailed Design Consultancy (DDC) for Phase 1’s elevated viaduct, stations, transition spans & depot at Bhesan. Line-1: Sarthana to UG Ramp and Line-2: Bhesan to Saroli | ||
DDC | RITES – RINA Consulting | Development of Multi Modal Integration | ||
DDC | RINA Consulting | Tunnel Ventilation System (TVS) and Environment Control System (ECS) for underground tunnels and stations | ||
DDC | Ardanuy Ingeniería S.A. – RITES JV | Detailed Design Consultancy (DDC) for Power Supply & Distribution System, 750 V DC Third Rail Traction Electrification and SCADA System | ||
EIA/SIA | LEA Associates South Asia Pvt. Ltd. | Independent Environmental and Social Consultant | ||
Consultant | Ernst & Young LLP | Consultant for PPP AFC System by Open Loop EMV and RUPAY based ticketing | ||
Package DC01 | ITD Cementation India | Civil construction of Dream City Depot, Operations Control Centre (OCC) and Metro Bhavan | ||
Package CS1 | Sadbhav Engineering – SP Singla Construction JV | Construction from Kadarsha Ni Nal to Dream City (11.6 km viaduct & 10 stations) | ||
Package CS2 / UG-1 | Gulermak – Sam India Builtwell JV | Construction from Kapodra Ramp to Surat Railway Station (3.46 km underground section – tunnels with 3 stations) | ||
Package CS3 / UG-2 | J Kumar Infraprojects | Construction from Surat Railway Station to Chowk Bazar Ramp (3.56 km underground section – tunnels with 3 stations) | ||
Package CS5 | Not yet finalize | Construction from Bhesan to Majura Gate Station including viaduct ramp to Bhesan Depot (10.559 km viaduct and 11 stations) |