Efkon India Bags ₹103 Crore Telecom Systems Contract for Mumbai Metro Lines 7A and 9
Bids invited for Telecommunication Systems Contract for Kochi Metro Phase 2 Pink Line
KMRL invites bids for supply of Heavy-Duty Escalators for Kochi Metro Phase 2 Pink Line
Spain floated €357.6 Million civil works tender for Burgos–Vitoria High-Speed Rail Line
Wabtec bags multiple contracts to supply over 680 Pantographs for Rail & Metro projects in India
Titagarh Rail bags major Rolling Stock contract for Ahmadabad Metro Phase 2 and Surat Metro
Indian Railways restructures Railway Board, Redeploys 50 Senior Officers to Field Duty
T&T Infra–Univastu JV Bags ₹229.97 Crore Civil Contract of Pune Metro Rail Project
Rail composites market set to reach $2.4 billion by 2028 as Railways embrace lightweight materials
Alstom powers Delhi Metro's Pink and Magenta Line with Driverless Trains and CBTC Signalling
New Delhi, India (Metro Rail Today): India’s first Bullet Train project continues to achieve key engineering milestones with the successful launch of the first 100-meter steel span over National Highway 48 near Nadiad, Gujarat. This span is part of a 2 x 100 m long steel bridge being constructed for the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor, under the ‘Make in India’ initiative.
The newly launched span, weighing around 1,414 metric tons and measuring 14.6 meters in height and 14.3 meters in width, was slid 200 meters across the six-lane NH-48 — one of India’s busiest highways — with minimal traffic disruption. The operation was executed using two semi-automatic jacks (each with a 250-ton lifting capacity) and supported by mac-alloy bars.
Fabricated at Salasar near Hapur, Uttar Pradesh, the bridge is designed for a 100-year lifespan and constructed using 57,200 Tor-Shear Type High Strength (TTHS) bolts. It features C5-grade protective painting and elastomeric bearings, and was assembled on trestles 14.9 meters above ground.
This bridge is one of 28 planned steel structures along the corridor — 17 in Gujarat and 11 in Maharashtra. To date, seven steel bridges have been launched in Gujarat, spanning over railways, highways, and industrial corridors.
Viaduct Construction: 293 km completed
Pier Works: 375 km
Pier Foundations: 394 km
Girder Casting: 320 km
Track Bed Construction: 143 km completed
Noise Barriers: 3 lakh installed over 150 km in Gujarat
OHE Mast Installation: 100+ masts installed between Surat and Bilimora (2 km stretch)
Par, Purna, Mindhola, Ambika, Auranga, Venganiya, Mohar, Dhadhar, Kolak, Vatrak, Kaveri, Kharera, Meshwa, and Kim.
Steel Bridges: 7 completed
PSC (Pre-Stressed Concrete) Bridges: 5 completed
21 km Mumbai–Shilphata Tunnel: 3.3 km excavated using NATM
Vikhroli & Sawli Shafts: Reached 56m and 39m depths respectively
Mountain Tunnels in Palghar, Maharashtra: 7 under construction using NATM
Gujarat Stations: Structural work complete at 6 out of 8 stations
Elevated Stations: All 3 under construction
Mumbai Station Excavation: 75% of 18.7 lakh m³ completed
Base Slab Concrete Poured: 25,000 m³ of 200,000 m³ total
Secant Piling at Mumbai Station: 100% completed (3,384 piles)
The project continues to push ahead at record pace, with advanced civil engineering techniques ensuring timely progress across both Gujarat and Maharashtra.
The 508 km (Gujarat & DNH: 352 km, Maharashtra: 156 km) Mumbai-Ahmedabd High Speed Bullet Train Corridor will have a total of 12 stations at Mumbai, Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.