General Information
Project Summary
- Project Name: Mumbai Metro Rail Project
- Nodal Body: Mumbai Metropolitan Region Development Authority (MMRDA)
- Owner: Govt. of India and Govt. of Maharashtra
- Project Type: Mass Rapid Transit System (MRTS)
- Total Network Planned: 339.6 km
- Estimated Project Cost: ₹1,53,384 Crore
- Operation Network: 11.4 km
- Operational Since: 8th June 2014
Project Information
Red Line – Line-7: Dahisar East – Andheri East
- Length: 16.495 km
- Type: Elevated
- Depot: Dahisar and Malvani (temporarily shared with Yellow Line)
- Project Cost: ₹ 6208 crore
- Number of Stations: 14
- Stations Names: Dahisar (East), Ovaripada, National Park, Devipada, Magathane, Mahindra & Mahindra, Bandongri, Pushpa Park, Pathan Wadi, Aarey, Mahanand, JVLR Junction, Shankarwadi, and Andheri (East).
Red Line – Line-7A: Andheri East – CSIA Terminal 2
- Length: 3.17 km
- Status: Under Construction
- Type: Elevated & Underground (2.915 km)
- Number of Stations: 2
- Stations Names: Airport Colony & CSIA Terminal
Red Line – Line-9: Dahisar East – Mira Bhayandar
- Length: 11.38 km
- Status: Under Construction
- Type: Elevated
- Number of Stations: 7
- Stations Names: Pandurang Wadi, Miragaon, Kashigaon, Sai Baba Nagar, Meditya Nagar, Shaheed Bhaghat Singh Garden and Subhash Chandra Bose Ground
- Detailed Project Report (DPR): View Here
- Estimated Cost: Rs. 6,518 crore (Line-7A & Line-9)
Project Cost & Funding:
Phase |
|
Project Cost |
|
Funding By |
Red Line 7 |
|
₹ 6,208 Crore |
|
Govt. of India and Govt. of Maharashtra |
Red Line 7A |
|
₹6,518 Crore |
|
Govt. of India and Govt. of Maharashtra |
Red Line 9 |
|
₹ 6,518 Crore |
|
Govt. of India and Govt. of Maharashtra |
Deadline: 7 (March 2022)
Technical Information
- Design Speed: 80 kmph
- Average speed: 33 kmph
- Track Gauge: 1,435 mm Standard gauge
- Electrification: 25 kV 50 Hz AC through
- Signalling System: Communications-based Train Control (CBTC)
- Rolling stock: NA
Major Contractors
- Delhi Metro Rail Corporation (DMRC): Interim Consultant
- Ayesa Ingenieria Y Arquitectura SAU – Itelferr – Consulting Engineers Group – Ayesa India (AICA Consortium): Line-7 General Consultant (GC)
- SYSTRA – Consulting Engineers Group Ltd – SYSTRA MVA Consulting (India) Ltd. (GC) : Line-7A & Line-9 General Consultant
- Ayesa Ingenieria Y Arquitectura SAU (DDC): Line-7 Detailed Design Consultant
- BEML (MRS1): Rolling Stock (576 Coaches for Yellow & Red lines)
- Alstom Transport India Ltd. – Alstom Transport SA (MS-01): Train Control, CBTC Signaling and Telecommunication system
- Cranex Ltd. (CA-180): Elevators at 13 stations (Andheri – Ovaripada) of Line-7
- Johnson Lifts Pvt. Ltd. (CA-19): Escalators at 13 stations (Andheri – Ovaripada) of Line-7
- Mitsui & Co. Ltd. (CA-20): Supply of 1080 Grade Head Hardened (HH) Rails
- Design, supply & installation of Ballastless Track System (CA-21): ITD Cementation India Ltd.
- Datamatics Global Services Limited (DGSL) and AEP Ticketing solutions S.R.L, Italy (AEP) (CA-33): Automatic Fare Collection (AFC) System
- L & T Construction (CA-58): Traction, Auxiliary Power Supply and SCADA
- Leena Powertech Engineers Pvt. Ltd – Cimechel Electric Company JV (CA-65): Overhead Electrification (OHE) Traction System
- CRRC Zhuzou (MS-03): Half Height Platform Screen Doors (PSDs)
- Simplex Infrastructures Ltd. (CA-01): Andheri East – New Ashok Nagar (viaduct & 5 stations)
- J Kumar Infraprojects Ltd. (CA-02, CA-48 & CA-91): New Ashok Nagar to Mahindra & Mahindra (viaduct & 6 stations), Dahisar East to Mira-Bhayander (viaduct & 7 station) AND Andheri East to CSIA T2 (viaduct, tunnels & 2 stations) & Balance viaduct construction of CA01: Andheri East to Aarey
- NCC Ltd. (CA-03 & CA-92): Mahindra & Mahindra to Dahisar East (viaduct & 5 stations) & Balance construction of 4 stations at Andheri Metro (East), Shankarwadi, JVLR Junction, Mahanand
- MPIL Steel Structure & RCC Eco Build Systems (CA-15A(R)): Design, fabrication & erection of steel roof structure on Line-7’s stations (2 contracts)
- Capacite Infraprojects, C.B. & Sons Constructions Pvt. Ltd & Landmark Corporation Pvt. Ltd. (CA-32): Architectural Finishing at Line-7 Stations (3 contracts)
- Jindal Steel & Power Ltd. (JSPL) (CA-159): 6800 MT of head-hardened rails for Line-9 and Line-5
Progress So Far
NA
In-depth Information