Track laying work completed in 17 km priority section of Delhi-Meerut RRTS corridor

MRT Online Desk Posted on: 2022-12-28 10:10:00 Viewer: 948 Comments: 0 Country: India City: New Delhi

Track laying work completed in 17 km priority section of Delhi-Meerut RRTS corridor

New Delhi, India (Metro Rail Today): The National Capital Region Transport Corporation Ltd (NCRTC) has completed the track laying work on the 17-km long Priority Section of the Delhi-Ghaziabad-Meerut RRTS corridor. About 34 km of track (17 km viaduct) has been laid in this section to make RRTS operational. Along with this, the installation of OHE and Signalling equipment in the Priority Section is also progressing at pace. So far, the installation of over 75 per cent Over Head Equipment (OHE) on the viaduct has been completed.

The construction of the viaduct was completed in the Priority Section in the month of October, following which the installation of OHE began. At present, more than three-fourths of this work has been completed. Soon the OHE being installed over the RRTS track will be energised with a capacity of 25,000 volts. To supply power for the operations of the Priority Section, an agreement has been signed with Uttar Pradesh Power Transmission Corporation Limited (UPTCL) in Uttar Pradesh.

With the completion of the track laying process, NCRTC has crossed a major milestone towards the implementation of RRTS. Preparations for the trial runs in the Priority Section are being carried out at a pace.

Four RRTS trainsets have already reached Duhai Depot and presently various dynamic and static testing are being carried out on them. NCRTC has also successfully completed the dynamic test run of the RRTS trainset with the ETCS- 2 signalling over LTE communication network, on the test tracks in Duhai Depot. The test run was successful and the Signalling system and the RRTS trainset operated with each other as per the technical expectations.

There are 5 stations in this entire section - Sahibabad, Ghaziabad, Guldhar, Duhai and Duhai Depot. At present, the finishing touches as well as the installation of escalators and lifts are being carried out at these stations The construction of amenities for commuters and counters is also in the final stages.

NCRTC has set a target to start operating RRTS trains in the Priority Section by next year in March and on the entire corridor in 2025.

  